Cost Baseline (Reference Example)

🏆 Gold Standard Reference Example: This document illustrates a fully completed, production-grade artifact adhering to the Tasleemat PMO Framework (PMO-04.04). All company names, project references, and figures are realistic fictional simulations.


Apex Global Solutions

Apex Unified Cloud ERP & Supply Chain Modernization - PRJ-2026-ERP-01

COST BASELINE

Date Prepared: 2026-03-15 Project Manager: Faisal Al-Harbi, PMP Prepared By: Faisal Al-Harbi, PMP (Senior Project Manager)

1. Time-Phased Cost Baseline (S-Curve)

Reporting Period and Planned Expenditures: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.

Cumulative Planned Value (S-Curve PV): Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.

Budget at Completion (BAC) Total: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.


2. Work Package Budget Allocations

Control Account and Work Package Allocations: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.

Contingency Reserve Distribution: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.


3. Project Funding Requirements and Limits

Periodic Funding Requirements: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.

Management Reserve and Total Project Budget: Preapproved Financial Resources & Budget Envelope: * Total Approved Capital & Operational Envelope: $3,500,000 USD, structured as: - Cloud SaaS Licensing & Infrastructure Subscription: $1,350,000 USD. - Systems Integration & Professional Engineering Services: $1,450,000 USD. - Organizational Change Management & User Enablement: $350,000 USD. - Management Contingency Reserve (10%): $350,000 USD.


Sign-off and Approvals

Role Name Signature Date
Project Manager Faisal Al-Harbi, PMP [Electronically Signed] 2026-03-18
Finance Controller / CFO Approved - Finance Controller Name [Electronically Signed] 2026-03-18
Project Sponsor Dr. Muna Al-Ghamdi (Executive VP of Technology) [Electronically Signed] 2026-03-18
---