🇸🇦 العربية Mohamed Fouad Fakhruldeen

Tasleemat Forms Guide

Project Artifact: Release Plan

Document Reference: PMO-04.03.09

This document provides a comprehensive, professional reference to understand the purpose and effective usage of the Release Plan in alignment with the Tasleemat framework.


1. What?

A formal Tasleemat-aligned project document known as the Release Plan, which is similar to a roadmap and functions as a high-level schedule showing which release each requirement or user story will be assigned to. The contents of a release can change according to the relative priority of the requirements in the backlog and the availability of the resources needed to work on them.

The plan can be elaborated into sprints, several to a release, and once a sprint starts its contents cannot change. It is therefore a forecast rather than a commitment, and stays dynamic throughout the project as priorities shift and new requirements are identified.

The form records a release table (release, dates, user stories, release goal, status) and a sprint breakdown (sprint, dates, goal, user stories, status).


2. Why?

To give the customer and the team a shared view of what is coming and when, and to keep the release sequence honest as priorities shift, so that what is promised is traceable to a backlog identifier rather than to recollection.


3. When?

This artifact is prepared at the PLANNING Process Group, under Schedule. A high-level plan may be developed once the product vision and the backlog have started, and it is re-sequenced after each sprint as priorities shift and new requirements are identified.


4. Who?

Responsibilities: Maintained by the Product Owner with the Project Manager, reviewed after every sprint, and agreed with the customer for committed releases. the ordering and for its accuracy. Estimated, reviewed, and updated by the team.


Tailoring Tips


Alignment & Dependencies

1. Pre-requisites & Inputs (Upstream Dependencies)

2. Downstream Dependents


5. How?

To accurately and professionally complete the RELEASE PLAN, the responsible party must populate the following sections based on the project context (ensure parameters.md is referenced for global project variables):


📥 Associated Templates


6. Reference Example

A fully completed, gold-standard reference example illustrating this artifact in practice is available:

📖 Completed Example: 04_03_09_Release_Plan_Example.md