PMO-00.02 00. Program & Portfolio Management Authoring & Governance Guide

Tasleemat Forms Guide

Project Artifact: Program Charter

Document Reference: PMO-00.02

This document provides a comprehensive, professional reference to understand the purpose and effective usage of the Program Charter in alignment with the Tasleemat framework.


1. What?

A formal Tasleemat-aligned project document known as the Program Charter, the document that authorises a program: why it exists, what it is accountable for delivering, and what authority and resources have been given to the program manager in order to deliver it.

It records the purpose and the business driver, the objectives with their measures and target dates, the component projects and which objectives they serve, the benefits and how they will actually be realised, the authority granted and the authority retained, the program-level risks and assumptions, and what happens when an objective is not met.


2. Why?

Because it is the point at which a group of individually sensible projects becomes a program with a single accountable owner and a single set of objectives. The separation of components from objectives is the part that matters: a program whose component list could be pasted into its objectives section has inherited its scope without choosing it, and a charter with no stated response to failure leaves that decision to whoever is in the room when it arises.


3. When?

This artifact is prepared at the PROGRAM AND PORTFOLIO MANAGEMENT Process Group, at the point the program is initiated and before any component project is funded against it.


4. Who?

Responsibilities: Sponsored by the executive who holds the funding and approves the charter. Owned by the Program Manager, who is accountable for delivering the objectives rather than for the components, since the components have their own owners. Reviewed by the PMO for consistency with the portfolio, and signed by the finance business partner who can confirm the funding position is real.


Tailoring Tips


Alignment & Dependencies

1. Pre-requisites & Inputs (Upstream Dependencies)

2. Downstream Dependents


5. How?

To accurately and professionally complete the PROGRAM CHARTER, the responsible party must populate the following sections based on the project context (ensure parameters.md is referenced for global project variables):


📥 Associated Templates


6. Reference Example

A fully completed, gold-standard reference example illustrating this artifact in practice is available:

📖 Completed Example: 00_02_Program_Charter_Example.md