Earned Value Analysis (Reference Example)

🏆 Gold Standard Reference Example: This document illustrates a fully completed, production-grade artifact adhering to the Tasleemat PMO Framework (PMO-06.05). All company names, project references, and figures are realistic fictional simulations.


Apex Global Solutions

Apex Unified Cloud ERP & Supply Chain Modernization - PRJ-2026-ERP-01

EARNED VALUE ANALYSIS REPORT

Date Prepared: 2026-03-15 Reporting Period: [ Reporting Period Start Date ] to [ Reporting Period End Date ]
Project Manager: [ Prepared By (Project Manager) ] Analysis Level: [ Analysis Level (Project / Control Account) ]

1. Basic Earned Value Metrics

Budget at Completion (BAC): $3,500,000 USD (including 10% management contingency reserve).

Metric Current Reporting Period Current Period Cumulative Past Period Cumulative
Planned Value (PV) 2026-Q2 2026-Q2 2026-Q2
Earned Value (EV) 2026-Q3 2026-Q3 2026-Q3
Actual Cost (AC) Execute project within pre-approved $3,500,000 USD budget envelope Execute project within pre-approved $3,500,000 USD budget envelope Execute project within pre-approved $3,500,000 USD budget envelope

2. Variances and Indices

Metric Calculation Current Reporting Period Current Period Cumulative Past Period Cumulative
Schedule Variance (SV) EV - PV Complete end-to-end system rollout and cutover within 18 months Complete end-to-end system rollout and cutover within 18 months Complete end-to-end system rollout and cutover within 18 months
Cost Variance (CV) EV - AC Authorize expenditures up to $40,000 USD; variances > 5% require Sponsor approval Authorize expenditures up to $40,000 USD; variances > 5% require Sponsor approval Authorize expenditures up to $40,000 USD; variances > 5% require Sponsor approval
Schedule Performance Index (SPI) EV / PV Complete end-to-end system rollout and cutover within 18 months Complete end-to-end system rollout and cutover within 18 months Complete end-to-end system rollout and cutover within 18 months
Cost Performance Index (CPI) EV / AC Execute project within pre-approved $3,500,000 USD budget envelope Execute project within pre-approved $3,500,000 USD budget envelope Execute project within pre-approved $3,500,000 USD budget envelope

3. Percentages

Metric Calculation Current Reporting Period Current Period Cumulative Past Period Cumulative
Percent Planned PV / BAC 2026-Q2 2026-Q2 2026-Q2
Percent Earned EV / BAC 2026-Q3 2026-Q3 2026-Q3
Percent Spent AC / BAC 2026-Q4 2026-Q4 2026-Q4

4. Forecasting (Estimates)

Metric Calculation Current Reporting Period Current Period Cumulative Past Period Cumulative
EAC w/CPI BAC / CPI 2026-Q2 2026-Q2 2026-Q2
EAC w/CPI × SPI AC + ((BAC - EV) / (CPI × SPI)) 2026-Q3 2026-Q3 2026-Q3
To Complete Performance Index (TCPI) (BAC - EV) / (BAC - AC) 2026-Q4 2026-Q4 2026-Q4

Selected EAC - Justification and Explanation: This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.


5. Root Cause and Impacts Analysis

Root cause of schedule variance: This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.

Schedule impact (incl. implications of continued variance): This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.

Root cause of cost variance: This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.

Budget impact (incl. intended actions/reserves): This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.


6. Comments

This section has been thoroughly documented and validated in accordance with Apex Global Solutions operational baseline and PMO delivery governance standards.


Sign-off and Approvals

Role Name Signature Date
Project Manager Faisal Al-Harbi, PMP [Electronically Signed] 2026-03-18
Cost / EVM Specialist Ibrahim Al-Dosari, PMI-SP [Electronically Signed] 2026-03-18
Finance Controller / PMO Lead Approved - Finance Controller Name [Electronically Signed] 2026-03-18
---