⚖️ Tasleemat Project Sizing & Tailoring Profiles Guide

Document Reference: TASLEEMAT-TAILORING-PROFILES-v2.0
Standard: PMI PMBOK® Guide 6th, 7th & 8th Edition Standard


🎯 Executive Overview

To prevent administrative bureaucracy on simple initiatives and ensure rigorous governance on critical investments, the Tasleemat Sizing and Tailoring Framework categorizes projects into 3 Governance Tiers and provides 5 Methodology Archetype Packs (general, agile, ai, predictive, hybrid).

Project Managers and PMO Directors use the Tailoring Plan (PMO-02.01) and AI Governance Plan (PMO-02.02) (or organizational complexity scoring) at Gate 1 to select the minimum mandatory artifact set required for their specific project.

flowchart TD
    subgraph Assessment["Gate 1: Project Categorization"]
        C1["PMO-02.01 Tailoring Plan"]
        C2["PMO-02.02 AI Governance Plan"]
        C1 --> Decision["Select Governance Tier & Pack"]
        C2 --> Decision
    end

    subgraph Tiers["Governance Sizing Tiers"]
        Decision --> T1["<b>Tier 1: Mega / Critical</b><br/>(>$10M | 35–50 Deliverables)"]
        Decision --> T2["<b>Tier 2: Standard</b><br/>($1M–$10M | 18–25 Deliverables)"]
        Decision --> T3["<b>Tier 3: Lean / Fast-Track</b><br/>(<$1M | 7–9 Deliverables)"]
    end

    subgraph Packs["Methodology Archetype Packs"]
        T1 & T2 & T3 --> P0["General PMO Pack"]
        T1 & T2 & T3 --> P1["Agile / Scrum Pack"]
        T1 & T2 & T3 --> P2["Predictive / EPC Pack"]
        T1 & T2 & T3 --> P3["AI & Data Product Pack"]
        T1 & T2 & T3 --> P4["Hybrid Transformation Pack"]
    end

🏛️ The Three Project Governance Tiers

🔴 Tier 1: Mega & High-Complexity Projects (Strategic Tier)

  • Profile Criteria:
  • Budget: $> \$10\text{M}$ (or $> 40\text{M}$ SAR).
  • Duration: $> 12\text{ months}$.
  • Complexity: High regulatory impact, cross-entity dependencies, multi-vendor contracting, high public exposure, or critical infrastructure impact.
  • Governance Cadence: Monthly Executive Steering Committee, bi-weekly PMO tollgates, weekly project core reviews.
  • Artifact Count: 35–50 Standardized Deliverables.
  • Mandatory Artifact Set:
  • Initiation: PMO-00.06, PMO-01.01, PMO-01.02, PMO-03.01, PMO-03.04, PMO-03.05, PMO-03.03.
  • Planning: Complete Project Management Plan (PMO-04.01.01), Scope Statement & WBS (PMO-04.02.05/06), Master Schedule Baseline (PMO-04.03.08), Cost Baseline & Reserves (PMO-04.04.04), Quality Plan (PMO-04.05.01), RACI Matrix (PMO-04.06.04), Communications Plan (PMO-04.07.01), Risk Register & Quantitative Modeling (PMO-04.08.02/04/07), Procurement Strategy & SOW (PMO-04.09.02/04), Stakeholder Engagement Plan (PMO-04.10.01), OCM Plan (PMO-04.11.01), ESG Plan (PMO-04.12.01).
  • Execution & Control: Status Reports (PMO-06.01), Earned Value Analysis (PMO-06.05), Issue Log (PMO-05.01), Decision Log (PMO-05.02), Change Control Log (PMO-05.04), Quality & Procurement Audits (PMO-05.05/PMO-06.07), Vendor Scorecards (PMO-06.09).
  • Closing: Deliverable Acceptance (PMO-06.08), UAT Sign-off (PMO-06.10), Handover Checklist (PMO-07.04), Contract Closeouts (PMO-07.02), Project Closure Report (PMO-07.03), Lessons Learned Summary (PMO-07.01), Post-Implementation Review (PMO-07.05), Benefits Plan (PMO-01.03).

🟡 Tier 2: Standard Enterprise Projects (Standard Tier)

  • Profile Criteria:
  • Budget: $\$1\text{M} - \$10\text{M}$ (or $4\text{M} - 40\text{M}$ SAR).
  • Duration: $3 - 12\text{ months}$.
  • Complexity: Standard organizational changes, internal systems development, moderate risk profile.
  • Governance Cadence: Bi-weekly Sponsor checkpoints, monthly PMO health checks.
  • Artifact Count: 18–25 Standardized Deliverables.
  • Mandatory Artifact Set:
  • Initiation: PMO-01.01, PMO-03.01, PMO-03.04, PMO-03.03, PMO-02.01.
  • Planning: Project Management Plan (PMO-04.01.01), Scope Baseline / WBS (PMO-04.02.06), Schedule Baseline (PMO-04.03.08), Cost Baseline (PMO-04.04.04), RACI Matrix (PMO-04.06.04), Risk Register (PMO-04.08.02), Communications Matrix (PMO-04.07.01).
  • Execution & Control: Project Status Report (PMO-06.01), Issue Log (PMO-05.01), Decision Log (PMO-05.02), Change Log & Requests (PMO-05.04/03), Variance Analysis (PMO-06.04).
  • Closing: UAT Sign-off (PMO-06.10), Deliverable Acceptance (PMO-06.08), Handover Checklist (PMO-07.04), Project Closure Report (PMO-07.03), Lessons Learned (PMO-07.01).

🟢 Tier 3: Lean & Fast-Track Projects (Lightweight Tier)

  • Profile Criteria:
  • Budget: $< \$1\text{M}$ (or $< 4\text{M}$ SAR).
  • Duration: $< 3\text{ months}$.
  • Complexity: Low technical risk, small collocated team ($< 8$ members), minimal cross-departmental impact.
  • Governance Cadence: Weekly standup, milestone sign-off with Sponsor.
  • Artifact Count: 7–9 Standardized Forms (Maximum Lean).
  • Mandatory Artifact Set:
  • PMO-03.01 Project Charter (Lean): High-level objectives, timeline, budget, and single-page scope statement.
  • PMO-04.02.08 Product Backlog / Activity List (PMO-04.03.02): Prioritized list of deliverable tasks and deliverables.
  • PMO-04.08.02 Risk Register (Simplified): Top 5 risks and immediate mitigations.
  • PMO-05.01 Issue & Decision Log (PMO-05.02): Operational tracking of blockers and decisions.
  • PMO-06.01 Project Status Report (One-Pager): Bi-weekly status flash for sponsor.
  • PMO-06.08 Deliverable Acceptance Form: Formal sign-off on delivered product.
  • PMO-07.04 Transition & Handover Checklist: Verification of handoff to operations.
  • PMO-07.03 Project Closure Summary: Final acceptance and lessons learned.

📦 Delivery Methodology Archetype Packs

Regardless of project size, teams augment their governance tier with specific Methodology Archetype Packs:

1. 🏃 Agile & Scrum Delivery Pack

  • Best for: Web applications, mobile apps, MVP releases, iterative digital solutions.
  • Specialized Forms:
  • PMO-03.02 Product Vision
  • PMO-04.02.08 Product Backlog
  • PMO-04.02.09 User Story Mapping Canvas
  • PMO-04.03.10 Sprint Planning Log
  • PMO-04.05.03 Definition of Ready (DoR) & Definition of Done (DoD)
  • PMO-04.06.05 Team Charter & Working Agreements
  • PMO-05.08 Sprint Retrospective
  • PMO-05.10 Impediment Log
  • PMO-06.12 Agile Flow Metrics & Cumulative Flow Diagram

2. 🏗️ Predictive & EPC Engineering Pack

  • Best for: Civil engineering, construction, physical infrastructure, industrial procurement.
  • Specialized Forms:
  • PMO-04.02.05 Detailed Project Scope Statement
  • PMO-04.02.06 Work Breakdown Structure (WBS) & Dictionary
  • PMO-04.03.05 Schedule Network Diagram (Critical Path Method)
  • PMO-04.04.04 Cost Baseline & S-Curve Cash Flow
  • PMO-04.09.02 Procurement Strategy & RFP Packaging
  • PMO-04.09.04 Statement of Work (SOW)
  • PMO-05.05 Quality Audit Log
  • PMO-06.05 Earned Value Analysis (EVM Report)
  • PMO-07.02 Contract Closeout Report

3. 🤖 AI & Data Product Governance Pack

  • Best for: Machine Learning models, LLM agents, Enterprise Data Warehouses, GenAI implementations.
  • Specialized Forms:
  • PMO-02.04 AI Canvas and Use Case Card
  • PMO-02.03 AI Ethics and Governance Checklist
  • PMO-02.06 Data Privacy and Ethics Assessment
  • PMO-02.05 AI Model Card and Fact Sheet
  • PMO-05.09 Prompt Library & Prompt Engineering Log
  • PMO-06.10 UAT Sign-off & Model Performance Validation

4. 🌐 Hybrid Value Delivery Pack

  • Best for: Enterprise ERP implementations, Core Banking replacements, Government Digital Transformation.
  • Specialized Forms: Combines Predictive Stage-Gates (0–2, 4–5) with Agile iterative execution during Stage 3 (Sprint Backlogs, Flow Metrics, Retrospectives).

📊 Summary Tailoring Matrix

Project Attribute Tier 1 (Mega) Tier 2 (Standard) Tier 3 (Lean)
Budget $> \$10\text{M}$ $\$1\text{M} - \$10\text{M}$ $< \$1\text{M}$
Duration $> 12\text{ months}$ $3 - 12\text{ months}$ $< 3\text{ months}$
Form Set Size 35–50 Forms 18–25 Forms 7–9 Forms
Steering Committee Mandatory (Monthly) Optional / Ad-hoc None (Sponsor Direct)
Earned Value (EVM) Mandatory (PMO-06.05) Recommended Optional / Variance only
Risk Management Quantitative Modeling Standard Register Top 5 Log
Change Control Formal CCB Board Sponsor Approval PM / Sponsor Verbal+Log