🔗 Tasleemat Document Dependencies & Lifecycle Network

Document Reference: TASLEEMAT-DOC-DEPENDENCIES-v2.0
Standards: Aligned with PMI PMBOK® Guide 6th, 7th & 8th Editions


🎯 Executive Overview

In the Tasleemat PMO Operating Framework, no deliverable exists in isolation. Every artifact operates as a node in a Directed Acyclic Graph (DAG) connecting strategic drivers, baselines, execution logs, and closure assets across all 8 phases:

flowchart TD
    G0["<b>Phase 00/01: Strategy & Value</b><br/>Business Case & OKRs"] --> G1["<b>Phase 02/03: Initiation & Approach</b><br/>Project Charter & Vision"]
    G1 --> G2["<b>Phase 04: Planning Baseline</b><br/>PMP, Scope, Schedule, Budget"]
    G2 --> G3["<b>Phase 05: Execution & Delivery</b><br/>Work Build, Issues & Change Requests"]
    G3 --> G4["<b>Phase 06: Monitoring & Control</b><br/>Status Reports, EVM & Quality UAT"]
    G4 --> G5["<b>Phase 07: Closing & Operations</b><br/>Handover, Closeout & Lessons Learned"]

📋 Comprehensive Deliverable Dependency Index (All 114 Deliverables)

Code Deliverable Name Lifecycle Gate / Phase Primary Inputs (Predecessors) Primary Outputs (Successors)
PMO-00.01 Portfolio Roadmap Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-00.02 Program Charter Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-00.03 Interdependency Register Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-00.04 Resource Capacity Matrix Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-00.05 PMO Maturity Assessment Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-00.06 OKR Alignment Matrix Gate 0: Strategic Alignment Corporate Strategic Objectives, Mandates Portfolio Roadmap, Program Charters
PMO-01.01 Business Case Gate 0: Concept & Feasibility Strategic Objectives, Problem Statement Approved Business Case, Benefits Plan
PMO-01.02 Benefits Management Plan Gate 0: Concept & Feasibility Strategic Objectives, Problem Statement Approved Business Case, Benefits Plan
PMO-01.03 Value Realization Register Gate 0: Concept & Feasibility Strategic Objectives, Problem Statement Approved Business Case, Benefits Plan
PMO-01.04 Gap Analysis Report Gate 0: Concept & Feasibility Strategic Objectives, Problem Statement Approved Business Case, Benefits Plan
PMO-02.01 Tailoring Plan Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-02.02 AI GOVERNANCE PLAN Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-02.03 AI Readiness Assessment Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-02.04 AI Use Case Canvas Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-02.05 AI MODEL CARD AND FACT SHEET Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-02.06 DATA PRIVACY AND ETHICS ASSESSMENT Gate 1: Approach & Tailoring Business Case, Strategy Documents Tailoring Plan, AI Governance Controls
PMO-03.01 PROJECT CHARTER Gate 1: Initiation & Charter Approved Business Case, Tailoring Plan Signed Project Charter, Stakeholder Register
PMO-03.02 PRODUCT VISION Gate 1: Initiation & Charter Approved Business Case, Tailoring Plan Signed Project Charter, Stakeholder Register
PMO-03.03 ASSUMPTION LOG Gate 1: Initiation & Charter Approved Business Case, Tailoring Plan Signed Project Charter, Stakeholder Register
PMO-03.04 Stakeholder Register Gate 1: Initiation & Charter Approved Business Case, Tailoring Plan Signed Project Charter, Stakeholder Register
PMO-03.05 STAKEHOLDER ANALYSIS Gate 1: Initiation & Charter Approved Business Case, Tailoring Plan Signed Project Charter, Stakeholder Register
PMO-04.01.01 PROJECT MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.01.02 CHANGE MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.01.03 PROJECT ROADMAP Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.01 SCOPE MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.02 REQUIREMENTS MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.03 REQUIREMENTS DOCUMENTATION Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.04 REQUIREMENTS TRACEABILITY MATRIX Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.05 PROJECT SCOPE STATEMENT Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.06 WORK BREAKDOWN STRUCTURE Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.07 WBS DICTIONARY Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.08 PRODUCT BACKLOG Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.02.09 USER STORY MAPPING CANVAS Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.01 SCHEDULE MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.02 ACTIVITY LIST Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.03 ACTIVITY ATTRIBUTES Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.04 MILESTONE LIST Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.05 NETWORK DIAGRAM Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.06 DURATION ESTIMATES Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.07 DURATION ESTIMATING WORKSHEET Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.08 PROJECT SCHEDULE Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.09 RELEASE PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.03.10 SPRINT PLANNING LOG Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.04.01 COST MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.04.02 COST ESTIMATES Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.04.03 COST ESTIMATING WORKSHEET Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.04.04 COST BASELINE Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.05.01 QUALITY MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.05.02 QUALITY METRICS Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.05.03 Definition of Ready and Done Standard Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.01 RESOURCE MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.02 RESOURCE REQUIREMENTS Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.03 RESOURCE BREAKDOWN STRUCTURE Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.04 RESPONSIBILITY ASSIGNMENT MATRIX Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.05 TEAM CHARTER Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.06.06 Team Psychological Safety and Wellbeing Index Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.07.01 COMMUNICATIONS MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.07.02 COMMUNICATIONS DISTRIBUTION MATRIX Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.01 RISK MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.02 RISK REGISTER Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.03 PROBABILITY AND IMPACT ASSESSMENT Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.04 PROBABILITY AND IMPACT MATRIX Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.05 RISK DATA SHEET Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.06 RISK REPORT Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.08.07 RISK MITIGATION ACTION PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.09.01 PROCUREMENT MANAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.09.02 PROCUREMENT STRATEGY Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.09.03 SOURCE SELECTION CRITERIA Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.09.04 Statement of Work Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.09.05 Request for Proposal Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.10.01 STAKEHOLDER ENGAGEMENT PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.10.02 STAKEHOLDER ENGAGEMENT ASSESSMENT MATRIX Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.11.01 OCM Strategy and Plan Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.11.02 Training Plan and Log Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.12.01 Sustainability and ESG Management Plan Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-04.13.01 INFORMATION SECURITY AND COMPLIANCE PLAN Gate 2: Planning Baseline Project Charter, Stakeholder Register Approved Baseline Plans (Scope, Schedule, Budget)
PMO-05.01 ISSUE LOG Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.02 DECISION LOG Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.03 CHANGE REQUEST Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.04 CHANGE LOG Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.05 QUALITY AUDIT REPORT Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.06 TEAM PERFORMANCE ASSESSMENT Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.07 LESSONS LEARNED REGISTER Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.08 RETROSPECTIVE Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.09 Prompt Library Log Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.10 Impediment Log Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.11 Meeting Minutes Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.12 Team Onboarding Checklist Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.13 ACTION ITEMS LOG Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.14 WORKSTREAM COORDINATION AND STANDUP LOG Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-05.15 DELIVERABLE TECHNICAL INSPECTION CHECKLIST Gate 3: Execution & Coordination Baseline Plans, Work Packages Completed Work Packages, Operational Logs
PMO-06.01 PROJECT STATUS REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.02 TEAM MEMBER STATUS REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.03 CONTRACTOR STATUS REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.04 VARIANCE ANALYSIS Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.05 EARNED VALUE ANALYSIS REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.06 RISK AUDIT REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.07 PROCUREMENT AUDIT REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.08 PRODUCT ACCEPTANCE FORM Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.09 Vendor Performance Scorecard Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.10 User Acceptance Testing Signoff Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.11 Project Health Check Matrix Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.12 Flow Metrics and Value Stream Dashboard Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.13 EXECUTIVE STEERING COMMITTEE DASHBOARD Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.14 MILESTONE TREND ANALYSIS AND SLIP CHART Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.15 DEFECT AND BUG TRACKING LOG Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-06.16 RISK AND ISSUE ESCALATION REPORT Gate 3: Monitoring & EVM Work Performance Data, Deliverables Status Reports, EVM Metrics, Acceptance Forms
PMO-07.01 LESSONS LEARNED SUMMARY Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.02 CONTRACT CLOSEOUT REPORT Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.03 PROJECT OR PHASE CLOSEOUT Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.04 Transition to Operations Checklist Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.05 Post-Implementation Review Report Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.06 KNOWLEDGE TRANSFER AND ASSET ARCHIVAL SIGNOFF Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned
PMO-07.07 ADMINISTRATIVE AND RESOURCE RELEASE FORM Gate 4/5: Handover & Closeout Verified Deliverables, Acceptance Signoffs Closed Contracts, Handover Records, Lessons Learned

NOTE

**Proposed Governance Framework Disclaimer**

The lifecycle predecessor and successor relationships defined in this matrix represent a recommended operational reference flow aligned with PMI / PMBOK® standards. Enterprise PMOs should adjust and tailor these dependencies according to project methodology, contractual arrangements, and internal workflow requirements.